Below, you will find descriptions of the resource period parameters used in standard modules (resource period data fields)

DI001326 Resource

ID of the resource

DI001327 Period

In PLANTA project, one period equates to one day. On this day, a resource can be planned, or vacation or absence can be specified for him or her.

DI001337 Available capacity (without child resources)

Actually available capacity of the selected resource and of all of its possibly existing child resources (summarized) in the selected period Do not confuse this with general General availability of the resource per period (Cf. Unit/period)! Due to different influence factors, the actually available capacity can be lower or higher than the defined availability. For further information, see the calculation below.

Details

  • When creating period records, the default value defined for the resource is consistently copied from the Available capacity for periods field (Resource Data Sheet module) to all periods but, if necessary, it can be changed for each period by changing the influence factor values (manual changing not possible since calculated).
  • If the default value or one of the values which are considered in the calculation is changed in the Available capacity for periods field (Resource Data Sheet module), the default value is automatically applied to all new periods of the resource as soon as they are generated. If the changed value is to be adopted for existing periods as well, the periods must be updated in the Resource Data Sheet module.

Calculation

  • Available capacity (without child resources) = Unit/period * Factor amount/period +/- values of the influence factor 1-5 (vacation, absence, factor value 3, factor value 4, or factor value 5) calculated successively.

DI002454 Available capacity

Actually available capacity of the selected resource and of all of its possibly existing child resources (summarized) in the selected period

Calculation (summarization)

Note

  • If the resource availability of the child resources is altered, the available capacity for each period will be summarized upwards along the resource structure when saving. It is saved in the Available capacity field on each parent resource per period.

DI001338 Factor amount/period

Amount available from the production factor particularly for the selected period. When creating the periods, the general, initial value is consistently copied from the Factor amount field (Resource Data Sheet module) to all period records but can be changed in individual period records afterwards.

Details

The parameter can be edited in the following module by users with modification rights:

DI001339 Unit/period

The number of units ( the unit itself is defined in the Base unit parameter), which are available for the planning of the selected resource in the selected period. When creating the periods, the initial default value is consistently copied from the Unit/day field (Resource Data Sheet module) to all period records but can be changed for individual period records afterwards.

The parameter can be edited in the following module by users with modification rights:

DI001340 Vacation (factor value 1)

In PLANTA standard, the vacation of the resource is displayed in the selected period (on the selected day). The field is automatically filled with the value which the respective employee has set when recording his/her Absence for this day: one day (1) or half a day (0,5) 

Details

  • The parameter represents the first of 5 influence factors with the help of which the generally defined availability of the resource per day (see the Available capacity (without child resources) parameter can be changed. This factor is permanently preset with vacation and cannot be changed. In the calculation of available capacity, the 5 period influence factors are successively taken into account.

DI001341 Absence (factor value 2)

In PLANTA standard, the vacation of the resource is displayed in the selected period (on the selected day). The field is automatically filled with the value which the respective employee has set when recording his/her Absence for this day: one day (1) or half a day (0,5) 

Details

  • The parameter represents the second of 5 influence factors with the help of which the generally defined availability of the resource per day (see the Available capacity (without child resources) parameter can be changed. This factor is permanently preset with vacation and cannot be changed. In the calculation of available capacity, the 5 period influence factors are successively taken into account.

DI001342 Basic load (factor value 3)

In PLANTA standard, the vacation of the resource is displayed in the selected period (on the selected day).

Details

  • The influence represents the third of 5 influence factors with the help of which the generally defined availability of the resource per day (see the Available capacity (without child resources) parameter can be changed. This influence factor can be set to another meaning if required, however, in such a case, the impact on the modules in which this parameter is used must be taken into account. In the calculation of available capacity, the 5 period influence factors are successively taken into account.
  • The field is automatically filled with the value from the Value 3 field in the Resource Data Sheet module, however, it can be changed manually per period (day) in the Availability module.

DI001343 Factor value 4

In PLANTA standard, the vacation of the resource is displayed in the selected period (on the selected day)

Details

  • The influence represents the fourth of 5 influence factors with the help of which the generally defined availability of the resource per day (see the Available capacity (without child resources) parameter can be changed. This influence factor can be set to another meaning if required, however, in such a case, the impact on the modules in which this parameter is used must be taken into account. In the calculation of available capacity, the 5 period influence factors are successively taken into account.
  • The field is automatically filled with the value from the Value 4 field in the Resource Data Sheet module, however, it can be changed manually per period (day) in the Availability module.

DI001344 Factor value 5

In PLANTA standard, a miscellaneous influence factor on the availability of the resource is displayed in the selected period (on the selected day) 

Details

  • The influence represents the fifth of 5 influence factors with the help of which the generally defined availability of the resource per day (see the Available capacity (without child resources) parameter can be changed. This influence factor can be set to another meaning if required, however, in such a case, the impact on the modules in which this parameter is used must be taken into account. In the calculation of available capacity, the 5 period influence factors are successively taken into account.
  • The field is automatically filled with the value from the Value 5 field in the Resource Data Sheet module, however, it can be changed manually per period (day) in the Availability module.

DI001346 Used (without child resources)

Actually incurring load (actual load) of the selected resource without its possibly existing child resources in the selected period (day) throughout all active projects. The value is automatically determined in replanning

Calculation

  • The Used (without child resources) value is determined from Actual load values of the resource from all projects in which it is planned.

Notes

  • The respective data field is hidden in the Availability module by default but the user can unhide it if required.
  • In this field, only the values from the projects with status = "Active" are displayed.
  • If the Work parameter = (deactivated), Used (without child resources) = 0

DI002464 Used

Actually incurring load (actual load) of the selected resource and of all of its possibly existing child resources (summarized) in the selected period (day)

Calculation (summarization)

Notes

  • The respective data field is hidden in the Availability module by default but the user can unhide it if required.
  • In this field, only the values from the projects with status = "Active" are displayed.

DI001352 Planned (without child resources)

Planned remaining load (remaining load) of the selected resource without its possibly existing child resources in all projects in the selected period (day) of all active projects. The value is automatically determined in replanning.

Calculation

  • In replanning, the Used (without child resources) value is determined from Remaining load values of the resource from all projects in which it is planned.

Notes

  • The respective data field is hidden in the Availability module by default but the user can unhide it if required.
  • In this field, only the values from the projects with status = "Active" are displayed.
  • If the Work parameter = (deactivated), Used (without child resources) = 0

DI001353 Planned code A (without child resources)

Planned remaining load of the selected resource without its possibly existing child resources in the selected period (day) throughout all active projects withCode = A in which this resource is planned.

Calculation

  • In replanning, the Planned code A (without child resources) value is determined from Remaining load values of the resource from the above mentioned projects.

Notes

  • By adjusting the value of the Utilization code 1 model parameter, the value of another project code can also be displayed in the Planned code A field.
  • If the Work parameter = (deactivated), Planned code A (without child resources) = 0

DI001354 Planned code B (without child resources)

Planned remaining load of the selected resource without its possibly existing child resources in the selected period (day) throughout all active projects with Code = B in which this resource is planned.

Calculation

  • In replanning, the Planned code B (without child resources) value is determined from Remaining load values of the resource from the above mentioned projects.

Notes

  • By adjusting the value of the Utilization code 2 model parameter, the value of another project code can also be displayed in the Planned code B field.
  • If the Work parameter = (deactivated), Planned code B (without child resources) = 0

DI001355 Planned code C (without child resources)

Planned remaining load of the selected resource without its possibly existing child resources in the selected period (day) throughout all active projects with Code = C in which this resource is planned.

Calculation

  • In replanning, the Planned code C (without child resources)  value is determined from Remaining load values of the resource from the above mentioned projects.

Notes

  • By adjusting the value of the Utilization code 3 model parameter, the value of another project code can also be displayed individually in the Planned code C field.
  • If the Work parameter = (deactivated), Planned code C (without child resources) = 0

DI001356 Planned code D (without child resources)

Planned remaining load of the selected resource without its possibly existing child resources in the selected period (day) throughout all active projects with Code = D in which this resource is planned.

Calculation

  • In replanning, the Planned code D (without child resources) is determined from Remaining load values of the resource from the above mentioned projects.

Notes

  • By adjusting the value of the Utilization code 4 model parameter, the value of another project code can also be displayed individually in the Planned code D field.
  • If the Work parameter = (deactivated), Planned code D (without child resources) = 0

DI001357 Planned code E (without child resources)

Planned remaining load of the selected resource without its possibly existing child resources in the selected period (day) in all active projects with Code = E in which this resource is planned.

Calculation

  • In replanning, the Planned code E (without child resources) is determined from Remaining load values of the resource from the above mentioned projects.

Notes

  • For individual adjustments you have to consider that here values from all projects are displayed, the codes of which do not correspond to any of the values of the Utilization code 1-4 model parameters. If projects with several such codes exist, their values are displayed summarized in the Planned code E (without child resources).
  • If the Work parameter = (deactivated), Planned code E (without child resources) = 0

DI002483 Planned

Planned remaining load (remaining load) of the selected resource and of all of its child resources (summarized) in the selected period (day)

Calculation (summarization)

Note

  • The respective data field is hidden in the Availability module by default but the user can unhide it if required.

DI002484 Planned code A

Planned remaining load (remaining load) of the selected resource and of all of its child resources (summarized) in projects the code of which equates to the value of the Utilization code 1 model parameter in the selected period (day). The values for the planned load stem from the planning of the respective resource in the Schedule.

Calculation (summarization)

DI002485 Planned code B

Planned remaining load (remaining load) of the selected resource and of all of its child resources (summarized) in projects the code of which equates to the value of the Utilization code 2 model parameter in the selected period (day). The values for the planned load stem from the planning of the respective resource in the Schedule.

Calculation (summarization)

DI002486 Planned code C

Planned remaining load (remaining load) of the selected resource and of all of its child resources (summarized) in projects the code of which equates to the value of the Utilization code 3 model parameter in the selected period (day). The values for the planned load stem from the planning of the respective resource in the Schedule.

Calculation (summarization)

DI002487 Planned code D

Planned remaining load (remaining load) of the selected resource and of all of its child resources (summarized) in projects the code of which equates to the value of the Utilization code 4 model parameter in the selected period (day). The values for the planned load stem from the planning of the respective resource in the Schedule.

Calculation (summarization)

DI002488 Planned code E

Planned remaining load (remaining load) of the selected resource and of all of its child resources (summarized) in all planning objects the Code of which does not correspond to any of the values in the Utilization code 1-4 model parameters, in the selected period (day). The values for the planned load stem from the planning of the respective resource in the Schedule.

Calculation (summarization)

DI001345 Utilization (without child resources)

Utilization of the selected resource without its possibly existing child resources in the selected period (day). Utilization means the sum of the planned remaining load and of the actual load throughout all projects in which the resource is planned.

Calculation

Note

DI002455 Utilization

Utilization of the selected resource and of all of its child resources (summarized) in the selected period (day)

Calculation (summarization)

DI001363 % utilization (without child resources)

Percentage value of the utilization of the selected resource without its possibly existing child resources in the selected period (day)

Calculation

DI059759 % utilization

Percentage value of the utilization of the selected resource and of all of its child resources (summarized) in the selected period (day)

Calculation

Note

DI001364 Work

With this parameter you can define whether the resource is available for planning in the selected period (day).

Values:

  • = work
  • = no work.
    • If the Work parameter is deactivated for a particular period, all other parameters mentioned above (Available capacity (without child resources), Utilization (without child resources), Planned (without child resources), Used (without child resources)) = 0 for this period

Details

  • When creating periods, this value is copied from the stored resource calendar.
  • In order to define a day as a non-working day in the Availability module, you have to empty the Unit/period and Factor amount/period parameters and save these changes. If this is done, the Available capacity (without child resources) and Available capacity fields will be emptied automatically if they contain values and the Work checkbox is automatically deactivated.
  • And vice versa, if you want to define a non-working day as a working day in the Availability module, the Unit/period and Factor amount/period parameters must be set, and in case the basic load is defined in the Resource Data Sheet, the Basic load (factor value 3) field with the appropriate value and the changes must be saved. As a result, the Work checkbox will automatically be deactivated.
  • After these parameters have been changed, replanning is required in order for the changed availabilities to be taken into account in all projects for which the resource has been planned.

DI002537 Vacation

Number of vacation days of the selected resource

Details

DI002538 Absence

Number of vacation days of the selected resource

Details

DI002544 Comment

Comment on the absence of the resource.

DI041435 Absence type

Type of absence

If the employees record their absence in the Absence module (or administrators in the Availability module), they must select an absence type for each day. The entry determines the type and duration of absence per day, i.e. either an entire or half a day. Different view modules for absence, e.g. Absence (Department), then do not show the specific absence type but only either Vacation or Absence with values 1 or 0,5. The tables below illustrate this relation.

Absence typeVacation field Absence field 
no entryblank:blank:
1/2 day absenceblank:0.5
1/2 day of vacation0.5blank:
Absenceblank:1
On- and off-the-job trainingblank:1
Maternity leave/parental leave1blank:
Special leave1blank:
Vacation1blank:


DI009478 Presence

Presence or hours to be worked of the selected resource in the selected period

Details

  • When using the clock in/clock out function, the presence of the employee will be saved here as soon as he/she has recorded presence in the course of working time recording.
  • When using the Hours to be worked function, the hours to be worked by employees can be specified here. The field is either filled automatically when setting the hours to be worked value in the Edit Hours to be Worked module or it can be edited manually in the Availability module.

DI063981 Histo: Available capacity + planned by code

Display of the available capacity and remaining utilization as a histogram by project code

DI041387 Week (period)

Calendar week with year specification

DI041388 Month (period)

Display of month and year

DI001673 Day

Numeric value of a weekday, whereas 1 = Monday and 7 = Sunday. Is used, e.g., for filtering by weekdays in the Availability module.

002488 Absence vacation: sum

Sum of all absence and vacation days per selected time period. The time period can vary in different modules.

 DI066137 Planned code A minus requested values

Planned remaining load of the selected resource and of all of its child resources (summarized) throughout all projects the Code corresponds to the value of the Utilization code 1 model parameter in the selected period (day), minus the requested values from Resource Requests

Calculation (summarization)

  • Planned code A minus requested values = sum of the Planned code A values of the selected resource and of all of its child resources in the selected period (day), minus the requested hours from Resource Requests.

 DI066138 Planned code B minus requested values

Planned remaining load of the selected resource and of all of its child resources (summarized) throughout all projects the Code of which corresponds to the value of the Utilization code 2 model parameter in the selected period (day), minus the requested values from Resource Requests

Calculation (summarization)

 DI066139 Planned code C minus requested values

Planned remaining load of the selected resource and of all of its child resources (summarized) throughout all projects the Code of which corresponds to the value of the Utilization code 3 model parameter in the selected period (day), minus the requested values from Resource Requests

Calculation (summarization)

 DI066140 Planned code D minus requested values

Planned remaining load of the selected resource and of all of its child resources (summarized) throughout all projects the Code of which corresponds to the value of the Utilization code 4 model parameter in the selected period (day), minus the requested values from Resource Requests

Calculation (summarization)

 DI066136 Planned code E minus requested values

Planned remaining load of the selected resource and of all of its child resources (summarized) throughout all projects the Code of which does not correspond to any of the values entered in the Utilization code 1-4 model parameters, in the selected period (day), minus the requested values from Resource Requests.

Calculation (summarization)

DI041389 Quarter (period)

DI041390 Year (period)

DI001661 Calendar week

DI002536 Vacation, absence, work=Y