You can mark tasks in which you are planned as "completed”.
To do so, activate the Completed checkbox in the line of the required task.
If the checkbox is activated, the actual end date will be set for the own planning in the task in question (the task itself does not have to be finished if other resources are still working on it) and
the task will either disappear from the display in the module after it has been refreshed
or it will be moved to the Non-postable objects (selected week)
Note
If you set the own planning for a particular task to Completed while there is still remaining effort, the remaining effort will be deleted in the next calculation of the schedule.