and, if resources are already planned, calculated start and end dates of the assigned resources as well as their loading and capacity adjustment.
Calculation of Successor Dates
Information
The network theory and the practical approach are available for determining the start of a task successor.
Network plan theoretical approach The successor starts on the day on which the predecessor ends.
Practical approach The successor does not start before the next day.
in PLANTA project
tasks with duration > 0 and EA relation are planned according to the practical approach, i.e. The successor starts on the following working day
tasks with duration = 0 (e.g. milestones) and EA relation are planned in the following way:
If the duration of a task = 0, you can define via the Successor task start +1 day model parameter when its successor is supposed to start.
If the successor of a task has a duration of = 0, the successor always starts on the same day as the task itself.
Details
Requested and actual dates which fall on non-working days (vacation, absence) remain as such and are taken into consideration in the scheduling of calculated dates. Start and end dates can thus also be planned on non-working days. The duration, however, is still displayed in working days. The resources are only loaded on working days.
Example
The TA Requested start of task A falls on Sunday, 11/10/2019, a non-working day. The start of task A is scheduled for the Requested start date.
Task B has no requested date, it therefore starts on the next working day.
Resource Ronja Koch is on vacation from 11/11/2019 to 11/15/2019. It is not scheduled during its vacation.