Calc. start and Calc. end of external tasks are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float <= 0 Since in PLANTA project the definition of requested dates on tasks leads to Total float = 0, tasks which do not necessarily lie on the critical path can be critical as well.
Calculated dates of external summary tasks
/
Milestones/master milestones of the external summary tasks