Notes on Actual dates

  • If an actual end is set without an existing actual start, then Actual start = Actual end.
  • In PLANTA, a task is not finished until an Actual end has been set. As long no Actual end en set for the task, task will be loaded with a Remaining duration of at least = 1, even if no Remaining effort is left.
  • Tasks with an Actual start or an Actual end behave during scheduling as in calculation with adherence to schedule, i.e. no capacity adjustment takes place. If the remainder of the task is to be adjusted anyway, it must be split with the help of the Split parameter.