When working with structured schedules, PLANTA recommends that you use summary tasks as structuring elements only, i.e. you should not carry out effort or cost planning or enter durations on this level. This includes resource planning or time recording directly to the summary task. Instead, PLANTA recommends that you carry out the planning on the child task only.
Reason: Since the scheduling detects some parameters of the summary tasks from child tasks, there may be collisions between your own planned values and those detected by the scheduling. As a result, there may be values on summary tasks that are incomprehensible at first sight.