to import a project structure for the selected project from an external system (currently SAP) via PLANTA link and possibly edit it, or
to manually create an SAP project structure or another alternative project structure or
to create account assignment elements and link them to SAP elements in order for the costs summarized to account assignment elements to be displayed on SAP WBS elements.
Details
The SAP project structure created or imported here (or an alternative structure) can be linked to the PLANTA project structure in the SAP-WBS or Schedule user modules in order to
either export the effort and costs planned in PLANTA project to the SAP system in line with the SAP project structure
or, in case costs and effort have been imported from the SAP system, to compare them to PLANTA effort/costs.
Note
Usually, the SAP WBS structure is imported to PLANTA including the already assigned account assignment elements.
The account assignment elements are required since they serve to import and export costs/effort and budgets from SAP to PLANTA project and vice versa.
ID of the account assignment elements equates to the ID of the cost type or cost center from which the costs or effort stem. If no account assignment elements exist on costs/effort, it is not summarized to the SAP WBS elements accordingly.
Create SAP WBS Elements Manually
Procedure
Select a PLANTA project from the Project name listbox.
Only projects with status = 1 will be displayed in the listbox.
Select Insert → SAP-WBS element from the context menu.
Enter the required data.
Save.
Create and Assign Account Assignment Elements Manually
Procedure
Right-click on the SAP WBS element to which an account assignment element is to be subordinated and select Insert → Account assignment element from the context menu.
Enter the ID or the cost type or cost center from which costs/effort are to be summarized in the Account assignment element field.
Save.
Delete SAP WBS Elements/Account Assignment Elements
Procedure
Mark the lines to be deleted.
Click on the button in the toolbar to delete the required line.
Note
An SAP WBS elements can only be deleted if
it is located on the lowest structure level, i.e. if no other SAP WBS element is assigned to it.
no effort or cost data from SAP is available on this SAP WBS element.
no PLANTA project tasks are assigned to this SAP WBS element.
Delete Assignment
Procedure
In this module you cannot assign SAP WBS elements to tasks, but available assignments can be deleted.
The assignment can only be made from the SAP-WBS module.
To delete an assignment, right-click on the required task and select the Delete assignment command from the context menu.