SymbolMeaningColorComment
Calculated dates of external tasks
uncritical
critical

Calc. start and Calc. end of external tasks are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float <= 0
Since in PLANTA project the definition of requested dates on tasks leads to Total float = 0, tasks which do not necessarily lie on the critical path can be critical as well.

Calculated dates of external summary tasks

/

Milestones/master milestones of the external summary tasks

 /  without delay
 /  with delay
 /  with Actual end

Without delay means: Total float >= 0
With delay means: Total float < 0

Requested dates of external tasks


Requested start and Requested end are defined in the Key dates area in the respective core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).