A gate is a master milestone of the planning objects.
Without date delay means:
Total float >= 0
With delay means:
Total float < 0
Gates are only displayed in the Schedule module if the
Schedule with gates checkbox has been activated in the
Project Core Data module in the core data module of the respective planning object