SymbolMeaningColorComment
Calculated dates of the programs

Calc. start and Calc. end of a program are calculated by clicking on the calculation button .

Gates

gate without date delay
gate with date delay
main gate/main milestone

A gate is a master milestone of the planning objects.
Without date delay means: Total float >= 0
With date delay means: Total float < 0

Gates are only displayed in the Schedule module if the Schedule with gates checkbox has been activated in the Project Core Data module in the core data module of the respective planning object