If the default cost center of the resource is changed (DT467), the new value is used for all resource assignments (DT466) that are created afterwards. The cost center of existing resource assignments, however, is not changed automatically, but equates to the default cost type applicable at the time of insertion of the resource assignment. It must be changed manually if required.
If the cost center of the resource assignment (DT466) is changed, it is applied to all new load records (DT472) of the resource assignment in the calculation of the project schedule. In order for the cost type to be applied to the existing load records as well, the schedule of the project must first be unloaded (Edit → Unload schedule menu item) and subsequently be recalculated (Edit → Unload schedule menu item).
Actual load records and manually created load records (i.e. those with MAN load profile) are exempt. They are neither changed during unloading nor in the calculation of the project schedule and must be adjusted manually if necessary.
Datenschutzhinweis
Wir verwenden Cookies und andere Technologien auf unserer Website. Mehr Informationen finden Sie hier: Datenschutzerklärung