If a resource is planned beyond the end of his/her planning horizon (i.e. later than the date of its end period), the impact on scheduling results must be considered.
To the BLD load profile, the following applies:
If there is no availability for planned resources due to missing periods, scheduling assumes that the availability is unlimited (7 days week) . The resource is scheduled for 7 days per week.
Since the distribution of the remaining hours on the task are done linearly, this leads to different calculations of calc. end dates of the task and the resource assignment.
To the CAP load profile, the following applies:
the entire remaining load is planned on one day, i.e. the first day after the end period.
To all other load profiles, the following applies:
loading in accordance with the load profile definition
If you do not want the system to behave in this way, you can proceed as follows:
Alternative 1: Prolongation of the planning horizon of the resource in the Resource Data Sheet.
However, to prevent performance impairment, the planning horizon should not be longer than necessary. The planning horizon can be extended if necessary.
Alternative 2: Scheduling of the resource using the MAN load profile.