• The project plans his/her projects in the Schedule module and assigns department resources (which can be planned freely) to the individual tasks.
  • Allocate the required Remaining effort for the individual resources.
  • Click on the button in the module header to put requests from the planning and open them in the Resource Requests module.
    • Alternatively, click on the button to switch to the Resource Requests module and click on the  button there.
  • The requests will be generated.
      • In project resource requests/approvals, one request will be generated per resource.
      • In task resource requests/approvals, one request will be generated per task.
      • The planned Remaining effort values are included in the request.
    • Write a comment in the Comment field if necessary.
    • Via  you can have a look at the utilization of the respective resource in the Utilization of module and the impact of the request can thus be simulated.
    • Click on to dispatch all requests or on to dispatch individual requests.
    • Confirm the query with Yes.
    • The requests will be approved and the status will be changed to in process