Procedure

  • If required, click on the Refresh button at the lower left module margin in order to refresh the data displayed in the module.
    • Click on the Refresh button will be displayed if a change has been made and was saved in another module of the project panel that might have an effect on data in the Status module.
  • Make the required changes in the Current status area (only estimate and comment possible).
  • Click on the Create baseline button in the header area of the module.
    • If there is no baseline report yet,
      • the following query will be displayed: Do you really want to create a baseline?
      • Confirm the query with Yes .
    • If there already is a baseline report
      • and you attempt to create a new baseline report, the Baseline report available for xxx!message will be displayed.
      • Confirm the message with OK .
      • Confirm the Do you really want to create a baseline? query with Yes .