If the sum of measure reduction values exceeds the probability of damage specified in the risk, the probability of damage is set to 0% in the calculation of the probable damage, which, however, is not explicitly visible on the surface.
Even if the probability of damage obtained by the measures can be reduced to 0%, the probable damage does not necessarily have to be 0 since the costs of the measures are included in the calculation.
Examples
Possible damage
Probability
Relative risk reduction
Relative measure costs
Probable damage
Case 1:
10000
50 %
-
-
5000
Case 2:
10000
50 %
20 %
1000
4000
Case 3:
10000
50 %
20 % 40 %
1000 1000
2000