• Create a new risk record by right-clicking on the module header or on an already existing risk record and selecting the Insert → Risk command from the context menu.
  • Enter the name in the Risk field.
  • Select the required category from the listbox.
  • The amount of damage possible due to the occurring risk is specified in the Possible field (EUR).
  • Enter the probability in the Probability field (in %).
  • The probable damage extent is calculated in the Probability field from the values in the Possible and Probable fields. If measures are subsequently added to the risk, their values are taken into account in the calculation of the probable damage as well.
  • If required, you can go ahead and fill other fields and save subsequently.

Note

  • All newly created risks are active by default (Active checkbox activated).
  • If risks are deactivated,
    • they will not be considered in evaluations and status reports.
    • they will not be displayed in the charts.
    • the probable damage in the Probable field is not calculated for such risks either.