Access

Information

  • In this module, load of resources per month is displayed.
    • If you have selected a department resource, the loads of the corresponding person resources will be displayed.
  • By expanding the tree structure on the projects, you can have individual tasks displayed.
  • Remaining load of the selected resource will be displayed on all levels.

Module variants

With actual loadsBy selecting this module variant, Actual load values will be displayed below the remaining load values in the time scale.

Note

  • Tasks for which the resource in question is planned and which already have an Actual end will be displayed grayed out.