SymbolMeaningColorComment
Task requested dates
Requested start and Requested end of a task are defined in the Schedule module.
Calculated dates of the selected resource for the selected task in the selected project.Upper part of the bar:
The color of the bar is determined by the code of the respective project
For the meaning of the individual code colors, see the histogram legend.

Lower part of the bar:
task uncritical
task critical

Calc. start and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.




Uncritical means: Total float > 0
Critical means: Total float <= 0
Since in PLANTA project the definition of requested dates on tasks leads to Total float = 0, tasks which do not necessarily lie on the critical path can be critical as well.

Actual dates of the selected resource for the selected task in the selected project.The bar is hatched in white.Actual start and last Latest time recording date of a resource in a task (resource assignment) will be calculated from the recorded hours worked of the corresponding resource (DT472) or they are edited manually.
Latest task dates

Latest start and Latest end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.

Task delay
A delay exists if Calc. end of a master milestone is later than its Latest end.