SymbolMeaningColorComment
Planned load (remaining load) of the resource(s) in projects
The color of the bar is determined by the code of the projects.
Code A
Code B
Code C
Code D
Code E
The code is defined in the Project Core Data of the respective project.
The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
Actual load of the resource(s)
The values for the histogram bar will be determined from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
Available capacity of the resource(s)
The values for the histogram bar will be determined from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will remain visible despite of overlapping by load data.
Basic load of the resource(s)
The values for the histogram bar will be determined from the Basic load (factor value 3) column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will remain visible despite of overlapping by load data.


or
20h

Overload of the resource
The overload percentage value displayed in the red bar or the absolute overload displayed as a red number will be determined from the availability of the resource (Summarized available capacity) and its planned loads (Summarized planned).