DT827 Load/report
DI008516 Project ID
Technical ID of the project
DI008517 Task
ID of the task
DI008519 Cost type
ID of the cost type which was entered on the selected load record
DI008523 Load date
Date of the load record at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT472 Load).
DI008535 Report
Code (ID) of the selected status report
DI040183 Report date
Date on which the selected status report was created
DI059487 Report name
Name of the selected status report
DI059488 Active baseline
Parameter that marks a status report as an active baseline. If multiple baselines have been created, the last created baseline is always marked as an active baseline.
DI008660 Planned load
Initially planned load of the resource on the selected day (in the selected load record) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT472 Load).
DI008662 Actual load
Actual load (hours actually worked) of the resource on the selected day (in the selected load record) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT472 Load).
DI008664 Remaining load
Remaining load of the resource on the selected day (in the selected load record) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT472 Load).
DI008661 Load planned-costs
Initially planned costs of the resource on the selected day (in the selected load record) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT472 Load).
DI008665 Remaining costs load
Remaining costs of the resource on the selected day (in the selected load record) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT472 Load).
DI008663 Actual costs load
Actual costs (calculated on the basis of hours worked) of the resource on the selected day (in the selected load record) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT472 Load).
DI057581 Total costs by resource type
#Total costs of all resources (except revenue resources) on the selected day (in the selected load record) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT472 Load).
DI029528 Total revenues by resource type
Total revenues of all revenue resources on the selected day (in the selected load record) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT472 Load).