Access

  • Project (Proposal) panel → ScheduleRead out Task Chain context menu command on the required task → Click on the required entry in the dialog module: Direct predecessor, Predecessor, Direct successor, Successor, Overall view.

Information

  • Depending on your selection in the dialog module, the direct predecessors/successors or all predecessors/successors or all predecessors and successors of the required task are selected.
  • When you open the module, the link to the direct predecessor and/or successor is displayed bold.

Details

  • If you click on another task within the displayed chain, the links of this task are visualized with predecessor and successor.