Assign Stakeholder to the Planning Object MOD0099IJ
Access
- Project (Proposal) panel → Project Core Data (Proposal Core Data) → Assign stakeholder button in the Stakeholder area → Assign stakeholder to the planning object
- Program (Proposal) panel → Program Core Data → Assign stakeholders button in the Stakeholder area → Assign Stakeholder to the Planning Object
Information
- This module is a dialog module and therefore it has no independent function. It is used to assign several persons to a project/proposal/program/request as stakeholders.
- Here all person resources (resources with resource type = 1i / 1e)
- which possess the Stakeholder person property and
- have not yet left the company are offered for selection.
Procedure
- Select the required resources by activating the Select checkbox.
- Click on the Assign selected objects button.