_BalkenLegenden_LegendTask
Symbol | Meaning | Color | Comment |
|---|---|---|---|
| Task requested dates | Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be enetered directly in the bar chart. | |
| Calculated dates of the tasks |
| Calc. start and Calc. end are calculated by clicking on the |
|
| Without delay means: Total float >= 0 | |
| Calculated dates of the summary tasks | A summary task is a task in the structured schedule consisting of sub-tasks which are summarized here. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. | |
| Actual dates | The respective bars are white hatched if the Splitting parameter is deactivated, and gray hatched if the parameter is activated. | Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the |
| Latest dates | Calc. start and Calc. end of a task are calculated by clicking on the | |
| Task delay | A delay exists if Calc. end of a master milestone is later than its Latest end. | |
| Task overlapping | Overlapping = possible delay of task successor when using soft links. For further information, see here. | |
|
|