No. | Use case | Result |
|---|
1 | Planning with Adherence to Schedule with Several Resources
Task with several task resources The Planned duration of the task is predefined. Planning type = adher. to schedule
| Scheduling carries out the planning along the duration of the task. Scheduling does not prevent overload. Overload will be indicated.
|
2 | Planning with Adherence to Total Float with Several Resources
Task with several task resources The Planned duration of the task is predefined. Planning type = adher. to total float
| Scheduling carries out the planning along the duration of the task. Scheduling does not prevent overload. The float of overloaded resources is not used to compensate possible overload. If there is not sufficient float, resources will be overloaded Resource 1 with overload: Float is used Resource 2 with overload: Starts at the earliest start date.
|
3 | Planning with adherence to capacity
Task with several task resources The Planned duration of the task is predefined. Planning type = adherent to capacity
| Scheduling plans the task without taking the Planned duration of the task into account. Resources are not overloaded. The float of the overloaded resource is used: Resources are not scheduled during non-working days.
|
4 | Resources with Vacation, Planning with Adherence to Schedule
| Scheduling carries out the planning block-wise. Scheduling does not plan the resource during its vacation period. On working days, the resource will possibly be planned with overload.
|
5 | Resources with vacation > Task duration, Planning with adherence to schedule
| The planning is scheduled before or at the start of vacation. The effort is displayed as overload due to the unavailability of the resource on vacation. If the entire task lies within the vacation period, it will be loaded at the calculated start date of the task.
|
6 | Planning with Adherence to Total Float with Vacation
Vacation is entered for a resource. Linear Load Profile The duration of vacation is shorter than the task duration. Planning type = adher. to total float
| Outside the vacation period scheduling carries out the planning block-wise. Available float is used. If the float is exhausted, scheduling will overload the resource. Resource is not planned during its vacation period. The planning is not splitted.
|
7 | Planning with Adherence to Capacity with Vacation
Vacation is entered for a resource. Linear Load Profile The duration of vacation is shorter than the task duration. Planning type = adherent to capacity
| |
8 | Planning with adherence to total float with Requested end and Fixing = 0
Task with several task resources The Planned duration is predefined. Requested end on a task Set the Fixing parameter = 0 The vacation of a resource is shorter than the task. Planning type = adher. to total float
| Scheduling plans the task on its Requested end. When setting Fixing = 0, the Requested end is exceeded if necessary. No consideration of float and possible overload since the specification of a Requested end causes loading with adherence to schedule. The task is not moved.
|
8.1 | Planning with adherence to total float with Requested end and Fixing = 1
| Scheduling plans the task on its Requested end. When setting Fixing = 1, the Requested end is adhered to and the task is loaded with adherence to schedule. Float and overloads are not taken into account. The task is not moved.
|
8.2 | Planning with adherence to Requested start on the resource assignment Task with several task resources
| |
9 | Planning with adherence to capacity with Requested end and Fixing = 1 Task with several task resources
| |
10 | Planning with adherence to schedule of a task with predecessor, Requested start and Fixing = 0
Vacation is entered for a resource. Linear Load Profile The duration of vacation is shorter than the task duration. Task with predecessor and Requested start, Fixing = 0 Planning type = adher. to schedule
| The task does not start at the Requested start but after the predecessor has ended. The vacation of the resource is taken into account. Remaining duration= Planned duration
|
11 | Planning with Adherence to Total Float with Effort > Availability
Task with several task resources The Planned duration is predefined. The capacity needed for the required duration exceeds the available capacity. Planning type = adher. to total float
| Scheduling exploits available float. If no more float is available, the task is planned block-wise at the latest possible point in time.
|
12 | Planning with Adherence to Capacity with Effort > Availability
Task with several task resources The Planned duration of the task is predefined. The capacity needed for the required duration exceeds the available capacity. Planning type = adherent to capacity
| Scheduling exploits available float. Scheduling is postponed until the block can be loaded in. The project end date is possibly exceeded. The resource is not planned during its vacation, the task is not splitted
|
13 | Planning with adherence to total float of a TA with predecessor, Requested end and Fixing = 0
Vacation is entered for a resource. Linear Load Profile The duration of vacation is shorter than the task duration. Task with predecessor and Requested start Fixing task parameter = 0 Planning type = adher. to total float
| The task does not start at the Requested start but after the predecessor has ended. The vacation of the resource is taken into account. Remaining duration = Planned duration Float is not exploited since a task with date is always automatically loaded with adherence to schedule.
|
14 | Planning with adherence to total float of a TA with predecessor, Requested end and Fixing = 0
Vacation is entered for a resource. Linear Load Profile The duration of vacation is shorter than the task duration. Task with predecessor and Requested start Fixing task parameter = 0 Planning type = adherent to capacity
| The task does not start at the Requested start but after the predecessor has ended. The vacation of the resource is taken into account. Remaining duration = Planned duration Float is not exploited since a task with date is always automatically loaded with adherence to schedule.
|
15 | Calc. start for reporting of several task resources
| Scheduling plans the resources with their remaining effort from the TAR Actual start on. If the day following the Actual start date is a non-working day, the resource will be scheduled for the next working day. The resource will possibly be overloaded.
|
16 | Reporting on Vacation
| Scheduling of resources without vacation is carried out in accordance with standard specifications. The resource who has reported during vacation is scheduled for the first working day following the reporting period. The resource will possibly be overloaded.
|
17 | Task with a resource The resource is on vacation from start to finish of the task Planning type = adher. to schedule, adher. to capacity, or adh. to total float Linear load profile (empty load profile)
| The resource is unavailable during the entire task duration Scheduling plans the entire remaining effort on the first day of the task duration Depending on the load type, the following behavior results: BLD (Load equals Actual effort/Max. load/day): It is only planned up to the maximum daily load. The rest remains untouched. CAP (adher. to capacity): The remaining effort is planned → this leads to heavy overload on the following day.
|