PLANTA project and Microsoft Project
The Import from Microsoft Project and Export to Microsoft Project functions are currently not available in the Web Client.
For information
In the following topic you will find information on the data exchange between PLANTA project and Microsoft Project.
In order to use the Microsoft Project interface, you have to license the PLANTA MSP link add-on. If you have any questions, please contact your PLANTA consultant.
For information
You can make PLANTA project projects available for Microsoft Project using the Microsoft Project export functionality.
The Microsoft Project import functionality allows you to
import projects from Microsoft Project to PLANTA project (initial import), or
import projects from Microsoft Project to PLANTA project that have already been exported from PLANTA Project to Microsoft Project (re-import).
Microsoft Project 2010, 2013, and 2016 versions are supported.
You can only import xml files.
In Microsoft Project you can convert a project to an .xml file via the Save as menu item.
Notes
A user can only export/import if he/she has modification rights for the project.
The project and its tasks are exported/imported with respect to their dates. Resources cannot be exported/imported.
The export of entire project structures (i.e. of projects including their subprojects) is not supported: each main or subproject of a project structure can only be exported individually.
See also: Further integration of PLANTA project
Export to Microsoft Project
Preparation
Procedure
Start PLANTA project.
Define a default working week under PM Administration → Master Data → Calendar.
Only deviations in the calendar for the defined standard working days are exported in order for the file size to be as small as possible.
Calculate the schedule of the project that is to be exported to Microsoft Project by clicking on the
button in the .module.
Execution
Procedure
Activate the Microsoft Project module in the project panel of the required project.
Click on the Export to Microsoft Project button.
The export procedure starts and the information window informs about the progress of the export procedure.
You can display details of the export procedure via the Details arrow.
If the export procedure is finished, a saving dialog for the generated MS Project XML file is displayed.
Save the file in the required directory.
Close the information window by clicking on the OK button.
Log Messages
If particular settings have not been made correctly, the following messages will be listed in the log:
Message | Reason |
|---|---|
| The calendar either starts after project start or it ends before project end |
| In the calendar used, default working days (checkboxes for Mo, Tue, Wed, Thu, Fri, Sat, Sun) are not activated |
| Both conditions mentioned above are not met. The calendar does not cover the project and there are no standard values that could be used |
The export of entire project structures (i.e. of projects including their subprojects) is not supported: each main or subproject of a project structure can only be exported individually.
Import the Generated XML File in Microsoft Project
Procedure
Open the generated XML file in Microsoft Project.
When you open the file, the import assistant is opened.
Import As a new project..
The import into Microsoft Project is completed and it can be edited.
Import from Microsoft Project
Information
If the project to be imported has initially been exported from PLANTA project, a reimport is carried out (regardless of whether you have imported to the original or to another project), otherwise, an initial import is carried out.
Please note:
The import is additive, i.e., if the same project is imported twice, all tasks will exist twice as well.
During the initial import, the data from Microsoft Project is imported directly into PLANTA project tables (DT461 Project, DT463 Task, DT465 Link).
When reimporting the data from Microsoft Project is imported into the comparison table (DT805 MSPITask and DT807 MSPIAOB). The PLANTA project data is not overwritten.
The meta data of the XML includes information on whether the project originally stems from PLANTA.
If you want to import a project that has already been exported from PLANTA as a new project anyway (i.e. carry out an initial import), please proceed as follows:
Display the following three PLANTA Project columns in Microsoft Project:
PLANTA MSPID
PLANTA TaskHash
PLANTA TaskID
Delete the contents from the three columns via Cut.
Save as an xml file.
Open the xml file with an editor.
Remove the content between
CODE<ExtendedAttributes>and
CODE</ExtendedAttributes>Save.
Import into PLANTA
Preparation
Prepare initial import
In Microsoft Project, save the project that you want to import in PLANTA project as an .xml file.
Create a new project in PLANTA project and open the Microsoft Project module.
Prepare reimport
Save the project exported from PLANTA project (and imported to MSP) as an .xml file in Microsoft Project.
Open the project into which you want to import from Microsoft Project in PLANTA project and switch to the Microsoft Project module.
Execution
Execution
Select the Import from Microsoft Project button in the Microsoft Project module.
Select the required .xml file and click on the Open button in the dialog window.
The import procedure starts and the information window informs about the progress of the export procedure.
You can display details of the export procedure by clicking on the Details arrow.
If the import is finished, close the information window via the OK button.
Open the PLANTA project vs. Microsoft Project module:
If an initial import is carried out, the imported project is displayed in the left window of the module.
If a reimport is carried out, the imported project is displayed in the right window and the initial one in the left window of the module.
Particularities
Parameter | Particularity |
|---|---|
WBS code | The WBS code is not imported from Microsoft Project but it is newly generated in PLANTA project. |
Project name | When importing a project from Microsoft Project into a project in PLANTA project, the name of the PLANTA project project will be overwritten with that of the Microsoft Project project. |
Task duration | Tasks which have a duration of zero days are displayed as milestones in Microsoft Project. You must take this into account when you carry out a reimport, because this way, normal tasks can unintentionally become milestones. Unlike in Microsoft Project, start and end dates set via requested dates can also be set to non-working days (weekend/holidays defined in the calendar), start and end of tasks of projects imported into Microsoft Project can be moved by this, since Microsoft Project sets the frame dates to a predecessor/successor date depending on the situation. |
Links to external tasks | They cannot be exported due to a local view on the project and different data models used in PLANTA project and Microsoft Project. |
Time intervals in links | When you export into Microsoft Project, time intervals are created for links (although they do not exist in PLANTA Project) or, if they are available in the source, they will be displayed incorrectly. However, this is not a bug but a result of different date calculation approaches in PLANTA project and Microsoft Project. Since a particular date constellation is not possible in Microsoft Project, the time intervals will be changed during the export process, so that the dates calculated in PLANTA at task level coincide with those in Microsoft Project. |
Dates in the past with active today line | If the Active today line parameter is activated and the dates from Microsoft Project lie in the past, PLANTA project would move the task dates to the current date (today). In order to prevent this, the planned dates from Microsoft Project (requested dates in PLANTA project) will be fixed via the Fixing parameter during the import procedure. |