Note

  • If the sum of measure reduction values exceeds the probability of damage specified in the risk, the probability of damage is set to 0% in the calculation of the probable damage, which, however, is not explicitly visible on the surface.
  • Even if the probability of damage obtained by the measures can be reduced to 0%, the probable damage does not necessarily have to be 0 since the costs of the measures are included in the calculation.

Examples

Possible damage Probability Relative risk reduction Relative measure costs Probable damage
Case 1:1000050 %--5000
Case 2:1000050 %20 %10004000
Case 3:1000050 %20 %
40 %
1000
1000
2000