Multi-project manager
Information
- Below you will find an explanation of what a multi-project manager is in PLANTA project and which modules are available for this role.
Role Function and Tasks
Information
- The multi-project manager’s core task is the coordination of several/all individual projects.
- The portfolio manager will place special emphasis on an optimal realization of strategic company goals.
- In single project analysis, multi-project managers should also identify resource conflicts across projects in good time in order to be able to take appropriate measures for optimization.
- Multi-project managers are also responsible for strategic project planning. They, e.g., define dates and carry out risk management.
Role Modules/Module Tree
The multi-project management modules can be accessed using the R41 demo user.
- Multi-Project Management
- Project Planning
- New Project (leads to the modules of the program workflow, see list under Projects)
- Multi-Project Board
- Projects (Link on a project ID leads to modules of the project workflow)
- Dashboard
- Project Core Data
- Budget
- Schedule
- WBS
- Status
- Info Board
- Costs and Effort.
- Effort Reports (is displayed if the project already contains effort)
- Effort Trend Analysis (is displayed if the project already contains effort and if there is at least one status report)
- Cost Reports (is displayed if the project already contains costs)
- Cost Trend Analysis (is displayed if the project already contains effort and if there is at least one status report)
- Costs and Revenues Total of the Project (is displayed if the project already contains costs)
- Resource Requirements (is displayed if the project already contains effort and if there is at least one status report)
- Dates
- Deviations (is displayed if there is at least one status report)
- Milestone Overview (is only displayed for main projects)
- Check Reported Hours
- Miscellaneous
- Opportunity Trend Analysis (is displayed if there is at least one status report)
- Risk Trend Analysis (is displayed if there is at least one status report)
- Costs and Effort.
- Resource Requests ( only available if Resource Planning with Requests/Approvals are activated)
- My Watchlist
- Unload
- Utilization by Skills
- Projects (Link on a project ID leads to modules of the project workflow)
- Replanning (Calculation of all Planning Objects)
- Program Planning
- New Program (leads to the modules of the program workflow, see list under Programs)
- Multi-Program Board
- Programs (Link on a program ID leads to modules of the program workflow)
- Dashboard
- Program Core Data
- Budget
- Schedule
- Status
- Dates
- Miscellaneous
- Opportunity Trend Analysis (is displayed if there is at least one status report)
- Risk Trend Analysis (is displayed if there is at least one status report)
- Dates
- My Watchlist
- Programs (Link on a program ID leads to modules of the program workflow)
- Reports
- Project Overviews
- Program Overviews
- Resource Overviews
- Cost Overviews
- Budget, Costs, and Revenues
- Budget, Costs, and Revenues (Delta View)
- Budget and Costs by Groups
- Budget and Costs by Customer, Group, and Manager
- Allocate Costs to Cost Centers
- Costs by Cost Type Groups
- Effort by Cost Type Groups
- Costs by Cost Types / Month
- Costs by Cost Type Groups / Month
- Costs and Revenues per Month
- Projects with Budget Overrun
- MPM Administration
- Project Planning
Note
- The modules of the planning object can be opened by clicking on a planning object ID.
- A list of the planning object modules and further information can be found under Project Panel, Proposal Panel, Idea Panel, Portfolio Panel or Program Panel.