Access

Information

  • In this module you can carry out a complete scheduling of all active planning objects and reorganize the capacity loading of the resources at period level. This ensures that there is reliable data on projects and resource utilization across all projects since  priorities among them are only taken into account when all projects are included in the calculation; i.e. of all projects which have common resources, those with the highest priority are loaded first and those with a lower priority then receive the remaining capacity of the resources in question. 
  • A replanning must also be carried out after changes have been made to company, project, and resource calendars or model parameters.

Details

  • This module shows all planning objects with status = 1 (active).
  • For projects with Level = 0 (i.e., simple projects or main projects in the case of project structures) will be displayed.
  • The planning objects displayed in this module are calculated in the following sequence:
  • During replanning, both the functional ID and the technical ID of the project which is being calculated are displayed in the status line. Once replanning is completed, the status line reads Replanning completed.

Procedure

  • After you have clicked on the Replanning button, replanning will be carried out in the following steps:
    1. All loaded planning objects are unloaded. This ensures that in a planning object the number of resources that are displayed does not exceed the number of resources that are loaded.
    2. Scheduling of all projects, proposals, ideas, and programs.
    3. Budget and cost scheduling of the project yearly costs of all projects, proposals, ideas, and subprojects
    4. Budget and cost scheduling of the subproject costs of all projects
    5. Budget and cost scheduling of the project costs of all projects, proposals, ideas, and subprojects
    6. Budget and cost scheduling of the program costs of all programs
  • When you click on the Replanning (incl. portfolios) button, the steps described above are carried out and finally the following step is carried out in addition:
    • 7. Budget and cost scheduling of the portfolio yearly costs of all portfolios

Notes

  • Since these calculations make use of extensive algorithms, replanning should not be carried out at times in which the server computer system is heavily loaded. The existence of a great number of projects with huge amounts of data also has an impact on the replanning runtime. We recommend that you run the replanning automatically over night. There are several ways to set this up. If you have further questions, please contact your PLANTA consultant.
  • The replanning is only carried out for the planning objects that are displayed in this module. This means that if, e.g., a replanning object was created after the Replanning (Calculation of All Projects) module had already been opened, and the replanning was initiated without prior module update, the newly created planning object was not considered in the replanning.
  • If a planning object was deleted in a session while the Replanning (Calculation of All Planning Objects) had already been opened, and the replanning was initiated after deletion of the planning objects, the deleted planning object was further displayed in the planning object list, but is no longer considered in the calculation since it no longer exists.
  • If one session is carrying out a replanning, it is not possible to delete one of the planning objects in another session. Upon attempt, the following message is output: Function is locked. Replanning active!
  • If replanning is running in a session, you cannot start single project calculation, unloading, or replanning in another session. This is indicated by a message.
  • If a network cycle is found in one of the planning objects included in the calculation, scheduling will be canceled here and a message will be displayed. After you have confirmed the message, scheduling is continued for the remaining planning objects, however, the planning object with network cycle is not calculated. The network cycle must be fixed in this planning object before it can be scheduled anew. For further information, please refer to Cycle Search.

For detailed information on the calculation of projects as well as on different factors which are to be considered and their impact, please refer to the Scheduling (Calculation of Projects) topic.