Programs
Information
PLANTA project offers an option to "bundle" projects with Program planning type. Under Planning Objects you will find information on further planning object types.
From a functional point of view, programs behave similar to main projects.
The structure of the respective editing or view modules equates to that of the project and only differs in the range of functions.
Only main projects can be assigned to a program. Any existing subprojects are thus also implicitly assigned, as their values are included in the budget, expense and cost values of the main project.
When you use the PLANTA Portfolio component, you have to make sure that a project is not assigned to a program and to a portfolio at the same time.
Programs can be copied to the portfolios just like other planning objects.
Note
Resource planning is not possible in the program schedules.
Details
Programs can merely be regarded as a bundling option for projects. There are no automatic links and Interactions between the programs and the projects assigned to them.
E.g., programs can be closed or quit even if their projects have not been quit or closed.
Exceptions:
If the Schedule with gates checkbox is activated in a project which is assigned to a program, not only project gates but also program gates (i.e., all existing gates) are displayed in the Schedule module.
The Program status of an active program can only be changed to "Archive" or "Inactive" if all assigned projects are also set to "Archive" or "Inactive".
Customizing Information
Programs are saved in DT461, just like projects, and are classified by means of a new Type = 30.
This means that scheduling (calculation of the schedule) for programs behaves just like scheduling for projects.
For the assignment of projects to programs, the Dependency data table is used. A code allows to distinguish whether these are dependencies between projects or an assignment to a program.