Note on actual dates

  • If an Actual end is set without an existing Actual start, then Actual start = Actual end

  • In PLANTA, a task is not finished until an Actual end has been set. As long as no Actual end has been set for a task, the task will furthermore only be planned with at least Remaining duration = 1, even if there is no more Remaining effort.

  • Tasks with an Actual start or an Actual end behave during scheduling as in calculation with adherence to schedule, i.e. no capacity adjustment takes place. If the remainder of the task is to be adjusted anyway, it must be split with the help of the Split parameter.