Structure the tasks hierarchically as required by moving them to the desired position by pressing SHIFT + holding down the left mouse button.
-
By clicking on the
Generate WBS code symbol (on the left side under the project bar).
-
The WBS code is generated automatically for every task in the WBS code field in accordance with the structure. Thus the WBS code is both a marker for individual elements in the work breakdown structure and an indicator of the hierarchical structure.
-
-
Start the calculation of the schedule by clicking on the Calculate schedule button in the action bar.
-
As a result, all parent tasks in the work breakdown structure are marked bold and are therefore visualized as summary tasks.
-
If the structure has been changed since the last update, the WBS codes are updated as well during the calculation of the schedule.
-