Dependencies between Tasks of a Project
Information
-
In PLANTA project, dependencies between tasks of a project are mapped in the form of links. For detailed information on this subject, see Links
Dependencies between Projects
Information
-
There are three ways to map dependencies between projects in PLANTA project:
-
Direct dependencies between projects
-
This function allows you to define one or more dependent projects for each project.
-
In the Dependencies module, you can create and look at dependencies between projects.
-
The dependencies created here are of purely informative nature and do not have an impact on the dates of the respective projects.
-
-
Cross-project links
-
Cross-project or external links connect the tasks of different projects.
-
Their effect is similar to that of links within a project, i.e. the cross-project links have an influence on the dates of all connected projects.
-
When calculating a project which is connected via external links, the projects it is connected to are included in the calculation. This results in the creation of a total network of all projects involved.
-
For detailed information, please click here.
-
-
External tasks
-
This function allows you to have tasks of another project/program displayed in the schedule of a project/program. You can, e.g., have milestones displayed which are decisive for your own project, which provides a clear overview within the project
-
The display of the tasks of a project in another project is of purely informative nature and has no impact on the dates of the projects involved.
-
For detailed information on external tasks, please click here.
-
-