Lock Time Recording

Information

  • The recording of hours worked can be locked or restricted via several parameters:

    •  globally

    • per project

      • with the Locked parameter in the Attributes/parameters area in the Project Core Data module. The recording/posting of actual data is thus not possible on any of the project tasks.

    • per task

      • with the Task locked parameter in the Schedule module. Using this parameter you lock the recording/posting of actual data for a particular task.


Customizing details 

  • In the module customizer you can use the Time recording lock parameter to define how the above mentioned parameters behave.


See also: Overview: Record Hours Worked , Lock Costs and Revenues postings