General
The results of scheduling include:
-
earliest start / end dates, latest start / end dates and calculated start / end dates on project level
-
earliest start / end dates, latest start / end dates and calculated start / end dates on project level
-
and, if resources are already planned, calculated start and end dates of the assigned resources as well as their loading and capacity adjustment.
Calculation of Successor Dates
Information
-
The network theory and the practical approach are available for determining the start of a task successor.
|
Network plan theoretical approach
|
Practical approach
|
-
in PLANTA project
-
tasks with duration > 0 and EA relation are planned according to the practical approach, i.e. The successor starts on the following working day
-
tasks with duration = 0 (e.g. milestones) and EA relation are planned in the following way:
-
If the duration of a task = 0, you can define via the Successor task start +1 day model parameter when its successor is supposed to start.
-
If the successor of a task has a duration of = 0, the successor always starts on the same day as the task itself.
-
-
Details
-
Requested and actual dates which fall on non-working days (vacation, absence) remain as such and are taken into consideration in the scheduling of calculated dates. Start and end dates can thus also be planned on non-working days. The duration, however, is still displayed in working days. The resources are only loaded on working days.