Calendar

Information

  • PLANTA supports the use of several calendars.

  • A basic calendar, which is used as a copy template for creating individual calendars, is supplied with the PLANTA software by default. New calendars are created in the Calendar module under Project Management Administration → Master Data.

  • In order to create calendars, the following decisions and information must be available:

    • Project time window: How far into the future do you want to plan?

    • When do statutory, regional or company holidays occur throughout the entire period?

Information on further master data and their creation, see here.