Post Costs MOD009ALO
Access
- PM Administration → PMO: Editing Modules → Post Revenues
- Project panel → Schedule → Post Revenues/Costs context menu command on a cost resource
Information
- In this module, the actual costs of the selected cost resources (resources with resource type = 9) recorded in the past 60 days are displayed.
- Further actual costs of the revenue resources can be recorded in this module.
Technical and Computational Information
- If you use PLANTA project for cost planning, the effort of the resources will automatically be converted into costs with the help of its conversion factors.
- The costs that have actually incurred (actual costs) thus result from the reported hours worked (actual load) of the resource and from the corresponding conversion factors.
- Since revenue resources do not have a reporting function for hours worked, their actual loads (Actual load) are recorded directly in the Post Costs module. I.e. no actual costs are directly recorded here but actual load of the cost resource which is only multiplied by the conversion factor in calculation of the schedule, resulting in actual costs which you can consult in the Schedule module of the respective revenue resource. Since for revenue resources this conversion factor is always 1, the calculated Actual costs value, which you can see in the Schedule module at the respective revenue resource, equates to the value recorded here in the Post Costs module. Further comprehensive information on cost planning, cost calculation, and cost viewing in PLANTA project can be found here.
Module Variants
Base | Shows the actual loads recorded within the past 60 days (actual costs) |
Including reverse postings | Like the base variant but with additional display of possibly canceled postings and of the respective reverse postings (if there are any). |
Post Actual Costs (Actual Loads of the Cost Resources)
Procedure
- Select a cost resource from the listbox in the Resource field.
- Open the context menu on the resource and select Insert → Costs.
- Select the date for which the costs are to be posted in the Date field.
- Select the required project and task and enter the amount of revenue in the Actual costs field.
- In the project listbox, only active projects the cost center of which equates to the cost center of the logged on user will be listed.
- In the task listbox, only tasks that have resource assignments and that are no milestones or master milestones will be listed.
Delete/Change Actual Costs (Actual Loads of the Cost Resources)
Information
- In some cases, actual values, or let alone entire actual load records, must not be deleted in PLANTA.
- The impermissible deletion or changing of actual values is prevented by PLANTA. In this case, reverse postings must be recorded for the postings to be deleted or corrected. Further information and reasons can be found here
Procedure for Automatic Reverse Postings
- From DB 13 you have the option to record automatic reverse postings
- If you use this option, you only have to delete or change the value in the Actual costs field of the required record. If reverse postings are required, they are created automatically in the background without the user taking note of it. The program virtually checks itself whether the requirements for reverse postings are met, and if so, it will take all required measures.
Procedure for manual reverse postings (if automatic reverse postings are deactivated)
- Actual costs are to be deleted
- Insert a new record below the load record to be canceled and set all values except Actual costs as in the original record.
- Enter the same value as in the original record with a minus symbol in the Actual costs field.
- Insert a new record below the load record to be canceled and set all values except Actual costs as in the original record.
- Actual costs are to be change
- Insert a new record below the load record to be canceled and set all values except Actual costs as in the original record.
- Enter the same value as in the original record with a minus symbol in the Actual costs field.
- Insert another record and set all values except Actual costs as in the original record.
- Enter the new cost value in the Actual costs field.
- Insert a new record below the load record to be canceled and set all values except Actual costs as in the original record.
- Cost type or date is to be changed
- Insert a new record below the load record to be canceled and set all values except Actual costs as in the original record.
- Enter the same value as in the original record with a minus symbol in the Actual costs field.
- Insert another record and set Actual costs as in the original record.
- Enter the required new cost type or date value.
- If a new parameter is only entered for one of the two parameters, the other value will remain the same as in the original record.
- Insert a new record below the load record to be canceled and set all values except Actual costs as in the original record.