Program
Information
- PLANTA project offers an option to "bundle" projects with Program planning type. Under Definition of Planning Objects you will find information on further planning object types.
- From a functional point of view, programs behave similar to main projects.
- The structure of the respective editing or view modules equates to that of the project and only differs in the range of functions.
- Only main projects can be assigned to a program. Any existing subprojects are thus also implicitly assigned, as their values are included in the budget, expense and cost values of the main project.
- When you use the PLANTA Portfolio component, you have to make sure that a project is not assigned to a program and to a portfolio at the same time.
- Programs can be copied to the portfolios just like other planning objects.
Note
- Resource planning is not possible in the program schedules.
Details
- Programs can merely be regarded as a bundling option for projects. There are no automatic links and Interactions between the programs and the projects assigned to them.
- E.g., programs can be closed or quit even if their projects have not been quit or closed.
- Exceptions:
- If the Schedule with gates checkbox is activated in a project which is assigned to a program, not only project gates but also program gates (i.e., all existing gates) are displayed in the Schedule module.
- The Program status of an active program can only be changed to "Archive" or "Inactive" if all assigned projects are also set to "Archive" or "Inactive".
Customizing Information
- Programs are saved in DT461, just like projects, and are classified by means of a new Type = 30.
- This means that scheduling (calculation of the schedule) for programs behaves just like scheduling for projects.
- For the assignment of projects to programs, the Dependency data table is used. A code allows to distinguish whether these are dependencies between projects or an assignment to a program.