Overview: Plan and Calculate Effort
Information
- Below you will find a brief tabular overview of the effort parameters for different project levels:
- Project level (PR),
- Task level (TA),
- Resource assignment level / Level of assignment of resources to a task (TAR)
- Load level / Level on which the effort of the resource is distributed to individual days (LOAD)
- This overview also provides a description of the behavior in both initial planning and calculation of already running projects.
- For a detailed description of the individual parameters, please use the links in the last column.
Description | If Actual start of the project = 0 (project is being planned) | If Actual start of the project > 0 (project has already started) | Parameters | |
---|---|---|---|---|
Remaining | Remaining value | Manual input in the resource assignment and subsequently
Exception: When you use the MAN load profile, the remaining values are entered at load level and are then summarized to resource assignment → task → project. |
Manual input or changes are only possible at resource assignment level. | Remaining effort (PR) Remaining effort (TA) Remaining effort (TAR) Remaining load (LOAD) |
Planned | Initially planned value This value is hidden in modules by default but the user can unhide it if required. | Automatic calculation: Planned = remaining If Remaining is changed, Planned will automatically be changed accordingly. | Planned = Remaining up to the point where an actual start date is set. From there on unchanged. Changes can still be made to Remaining after project start, however, Planned will remain unchanged | Planned effort (PR) Planned effort (TA) Planned effort (TAR) Planned load (LOAD) |
Actual | Actual value | 0 |
| Actual effort (PR) Actual effort (TA) Actual effort (TAR) Actual load (LOAD) |
Total | Sum value of Actual and Remaining | Automatic calculation on the respective level as soon as you have entered or changed Actual or Remaining and clicked outside the field. | Automatic calculation on the respective level as soon as you have entered or changed Actual or Remaining and clicked outside the field. | Total effort (PR) Total effort (TA) Total effort (TAR) Total load (LOAD) |