Information
- Resource Planning with Requests/Approvals
They can be configured in three ways:
-
globally
-
per project
-
per resource
-
-
Furthermore you can configure e-mail notifications for resource requests/approvals.
globally
Information
-
In the Global Settings module you can configure whether resource requests/approvals are to be activated globally.
-
Furthermore you can set the time grid within which resource requests can be created or approved.
Activate Resource Requests/Approvals
Information
-
Via the Resource requests active parameter in the Global Settings module you can configure whether resource requests/approvals are to be activated globally.
-
The selected setting is automatically selected for newly created projects.
Values
-
0: resource requests/approvals are inactive, i.e. all resources can be planned freely in the schedule. Modules and buttons which belong to resource requests/approvals are not visible.
-
1: project resource requests/approvals are active, i.e. resources with activated Approval required parameter must be approved at project level via the request/approval process.
-
2: task resource requests/approvals are active, i.e. resources with activated Approval required parameter must be approved at task level via the request/approval process.
Note
-
The parameter will be overwritten by the setting in the Resource requests field in the Project Core Data module.
-
If the setting is changed retroactively, this change only affects projects which are newly created after the change has been made.
Exclude requested resources from planning
Information
-
Via the Exclude requested resources from planning parameter in the Global Settings module you can configure whether the requested (generic) resource is automatically removed from the task when a resource approval is adapted in the schedule.
-
This setting is activated by default.
-
-
If the setting is deactivated, the project manager must remove the previously requested resources manually from the planning after approvals are adapted.
Configure Time Grid
Information
-
Via the Resource requests: time grid parameter in the Global Settings module you can configure in which time grid resource requests can be created or released.
Values
-
Set to months by default (value: 4).
-
Depending on the selected time grid, the resources will be loaded with the corresponding load profile.
-
2: Day (PM_DAY load profile)
-
3: Week (PM_WEEK load profile)
-
4: Month (PM_MONTH load profile)
-
5: Quarter (PM_QUART load profile)
Notes
-
The time grid setting also has an influence on default values for the display period of the time scale in the resource request modules.
-
Start of the time scale: date of the first request
-
End of the time scale:
-
2: date of the first request + 27 days
-
3: date of the first request + 96 days
-
4: date of the first request + 364 days
-
5: date of the first request + 454 days
-
-
-
If the setting is to be changed after requests have already been created, a query will be displayed asking whether the existing requests are to be archived. The setting will only be saved upon confirmation.
-
When changing the setting, the auxiliary
ApplyResourceRequestCustomizingChangesmigration packet, which adapts the modules to the selected setting, will be run. -
When changing the setting, existing approval exceedance will be marked as read. They can be viewed in the Approval Exceedance module.
-
Project
Information
-
The Resource requests parameter can be configured per project in the Edit Planning Objects module.
Details
-
inactive: resource requests/approvals are inactive, i.e. all resources can be planned freely in the schedule. Modules and buttons which belong to resource requests/approvals are not visible.
-
active at project level: project resource requests/approvals are active, i.e. resources with activated Approval required parameter must be approved at project level via the request/approval process.
-
active at task level: task resource requests/approvals are active, i.e. resources with activated Approval required parameter must be approved at task level via the request/approval process.
Notes
-
The listbox is only displayed in the Edit Planning Objects module if resource requests are activated at global level (Resource requests active = 1 or 2).
-
For new projects, the global setting is used by default. In the Edit Planning Objects module, the setting can be changed per project.
-
If the setting is to be changed after requests have already been created, a query will be displayed asking whether the existing requests are to be archived. The setting will only be saved upon confirmation.
-
If resource requests are activated in the project after resources have already been planned, no requests will be generated retroactively for these resources.
Resource
Information
-
For each resource you can configure via the Approval required parameter in the Resource Data Sheet whether there must be an approval for the resource when resource requests/approvals are activated.
Details
-
If the parameter is activated, the resource can only be planned if there is an approval at project or task level.
-
If the parameter is not activated, the resource can also be planned without approval.
-
The parameter is activated for person resources by default and is deactivated for all other resources.
-
In such a case, the department resource can be planned and requested, however the corresponding employees can only be planned and requested after approval.
-
If the parameter is deactivated for person resources, they will not be included in resource requests accordingly.
-
Notifications
Information
-
In order to be able to use e-mail notifications for Resource Planning with Requests/Approvals, several requirements must be met.
Details
-
In the recipient’s e-mail client, HTML mails must be supported and activated so that the resource request journal can be received.
-
In the Global Settings (Project) module, the IP address of the smtp-server must be specified in the SMTP server address parameter (the address which can be accessed externally).
-
In the Time-Controlled Events module, the time-controlled Send automatic e-mails for resource requests event must be activated.
-
In the Global Settings (MOD009ABF) customizing module under Customizer → Master Data
-
, the e-mail address of the sender must be specified in the Resource request journal: e-mail sender parameter.
-
the e-mail format can be adjusted if required.
-
Here, HTML must be used.
-
-
-
For sender and possible recipient, the Message via e-mail parameter must be activated in the Users module.
-
A department manager must be specified for the requested department in the Resp. for department parameter in the User field.