Post Costs MOD009DYT
Access
Project panel → Schedule → Post revenues/costs context menu command on a cost resource in the required task
Project panel → Schedule → Click on the link on the ID of the required task → Task → Post revenues/costs context menu command on a cost resource
Information
This module is a dialog module and therefore it has no independent function. It is used to record actual costs for the selected transaction.
When opening the module, the corresponding project and task are automatically preselected.
Procedure
Use the Plus button to add a new record for recording costs.
Record date and actual revenues in the Actual costs field and possibly write a comment.
Save.