Access

Information

  • This module provides the multi-project manager with an overview of already existing projects and proposals which the multi-project manager is authorized to view.
    • If they are structured projects, the subprojects can be expanded below the main projects.
  • In this module you can also create new projects. 

Module Variants

BaseAll active projects are displayed, i.e. projects with Status = 1 (active) and proposals.
Inactive projectsAll inactive projects are displayed, i.e. projects with Status = 2 (inactive).
Template projectsAll projects with Status = 0 (template) are displayed. These projects can be used as a template when creating a schedule in new projects.
Archived projectsAll archived projects are displayed, i.e. projects with Status = 9 (archive).
Overhead cost projectsAll overhead cost projects are displayed, hence projects with Posting type = 1 (Also future actual postings).

Details

  • The projects displayed in this module are grouped by code. It is, however, possible to change groupings or have projects displayed ungrouped.
    • In the Group by field you can either change the grouping criterion by making a selection from the listbox, or delete it. After you have clicked on the Use changes button, the projects are either displayed grouped by the selected criterion or they are displayed ungrouped.
      • If you change the grouping criterion in another module of the panel which also contains grouping criteria, it automatically takes effect in the current module as well.
  • The projects to be displayed in this module can be filtered using object filters.
    • If there already is an object filter, it can be selected from the listbox on the Filter field. After clicking on the Apply changes button, only projects which correspond to the filter are displayed.
    • You area, can edit existing object filters or create new ones in the Object Filter module which is opened via the Edit filter button.
    • If an object filter is selected in one of the modules which use object filters, it automatically takes effect in all other modules with object filters as well.


  • By clicking on the ID of the required project, you can switch to the corresponding Project panel, in which you can edit or have a look at the project data depending on your user rights.
  • By clicking on the New project button you switch to the Project panel in which a new project can be created.
  • If you unhide the Type column, you can see which planning object type the respective planning object is of, project or proposal.
  • By clicking on the arrows in the time scale area ( for incoming and for outgoing links), you can open and look at external links of the planning object in a dialog module. If you click on the arrow again, the dialog module is closed again.

Legend

SymbolMeaningColorComment
Requested dates
Requested start and Requested end are defined in the Key dates area in the respective core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
Calculated dates
The color of the bar is determined by the code of the planning object.
Code A
Code B
Code C
Code D
Code E

Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button .
The code of the planning objects is defined and changed in the Edit Planning Objects module (the code of projects and proposals can also be defined and changed in the Project Core Data and Proposal Core Data modules.

Actual datesThe bar is hatched in white. The background color depends on the code of the planning object.

Actual start and Actual end (if available, otherwise Latest time recording date ) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) during calculation of the schedule of the respective planning object by clicking on the calculation button .

Float
Float available when the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
Date delay
A date delay occurs when the calculated end date (Calc. end) is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
External links
outgoing
incoming

Master milestones

without delay
with delay
with Actual end

Tasks are defined as master milestones in the Schedule module.
Master milestone delay
Master milestone delay exists if Calc. end of a master milestone is later than its Latest end.