Tutorial: Structure Tasks

Objective of this tutorial

  • After this tutorial you can

    • create tasks in an empty schedule and number them with a WBS code,

    • subordinate tasks to another task via drag & drop in the Schedule module and thus create a summary task,

    • change the structure graphically in the WBS module and adjust the WBS code to the new structure.

Please note:

  • The screenshots used in this tutorial are mere examples of functions and may differ from the actual layout in the program.

Procedure

  • Call up the PLANTA Web-Client in the browser and click the field with the Multiprojektmanager role.

  • Create a new project.

  • In the project panel, click the Schedule tab.

    • The following query is displayed: How do you want to create your new schedule?

    • Click the Start blank button.

  • Open the context menu by right-clicking on the project line and select the Insert → Task entry.

    • Enter the name of the task in the Name field.

    • Enter the duration of the task in the Rem. duration field, in this example 10 days.

    • Save.

  • Create further tasks with a Rem. duration of 10 days as shown in the image below. To do so, right-click the task created last and select Insert → Task so that the new task is inserted below it.

  • Save and click the Calculate Schedule button in the action bar.

  • The WBS code is displayed in the Task column. Since the tasks have not been structured yet, it is only an ascending numbering.

PSP1EN.png
  • Test task x is to be subordinated to Test task.

    • To do so, drag Test task x onto Test task while holding down SHIFT and the left mouse button.

    • Test task x (source task) is visualized green and Test task (target task) blue.

    • As soon as the mouse pointer is on Test task, release the mouse button. Test task x is moved below Test task.

PSP4EN.png
  • Result: Test task x has been subordinated to Test task.

PSP4_ErgebnisEN.png
  • Test task y is also to be subordinated to Test task and positioned below Test task x.

    • To do so, drag Test task y below Test task x while holding down SHIFT and the left mouse button.

    • A dark blue line appears. Pay attention to the position of the line. It is to lie at the bottom edge of Test task x, and its starting point is to match the starting point of Test task x.

PSP5EN.png
  • Result:

    • Test task x has been subordinated to Test task.

    • Test task y has been subordinated to Test task and positioned below Test task x.

PSP6EN.png
  • Save and click the Calculate Schedule button in the action bar.

    • The WBS code is updated according to the structure defined before.

    • The parent Test task is displayed in bold and thus visualized as a summary task.

      • A summary task is a task in the structured schedule that consists of sub-tasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks.

PSP8EN.png
  • In the Project panel, switch to the WBS module by clicking the tab of the same name.

  • Here, the structure created in the Schedule module is displayed graphically.

PSP9EN.png
  • The structure is to be changed: Test task y is to be subordinated to Test task z.

    • To do so, position the mouse pointer over the left edge of the Test task y box: A hand symbol appears.

    • Hold down the left mouse button, drag the box to the Test task z box, and release it over this box.

PSP10EN.png
  • Result: Test task y has been subordinated to Test task z, but the old WBS code is still displayed.

PSP11EN.png
  • To update the WBS code, click the Rad_Mit_Rand.png Generate WBS code button at the top of the project bar.

  • Result: The code has been changed according to the new structure.

PSP12EN.png
  • In the Project panel, switch back to the Schedule module. Click the  Refresh/Reset button at the top right and the Calculate Schedule button in the action bar. The new structure and the new WBS code become visible here as well, and Test task z is also visualized as a summary task. Result:

PSP13EN.png

Summary

  • You have created four tasks in the empty schedule of a new project and numbered them consecutively by calculating the schedule.

  • In the Schedule module, you have subordinated Test task x and Test task y to Test task via drag & drop. After the schedule calculation, Test task is displayed in bold as a summary task.

  • In the WBS module, you have subordinated Test task y to Test task z and adjusted the WBS code to the new structure. Afterwards, Test task z is also a summary task in the schedule.