Project and Portfolio Management
Version 26 39.5.25 39.5.23 39.5.22 39.5.21 39.5.20 39.5.19 39.5.18 39.5.17 German English
Version 26 39.5.25 39.5.23 39.5.22 39.5.21 39.5.20 39.5.19 39.5.18 39.5.17 German English

Lock Cost and Revenue Posting

Information

  • The posting of costs and revenues can be locked or restricted via different parameters:

    • globally

    • per project

      • with the Locked parameter in the Attributes/parameters area in the Project Core Data module. The recording/posting of actual data is thus not possible on any of the project tasks.

    • per task

      • with the Task locked parameter in the Schedule module. Using this parameter you lock the recording/posting of actual data for a particular task.


Customizing details

  • In the module customizer you can use the Time recording lock parameter to define how the above mentioned parameters behave.


See also: Plan and Control Costs, Budget, Benefit, Revenues Lock Time Recording