DT824 Task report
Below, you will find descriptions of all task parameters which are used in modules and are frozen in status reports.
DI008443 Project ID/ID823
Technical ID of the project. It is generated automatically upon creation of the project and, unlike the functional ID, it cannot be changed afterwards. It is usually hidden in the modules.
DI008444 Project ID
Technical ID of the project. It is generated automatically upon creation of the project and, unlike the functional ID, it cannot be changed afterwards. It is usually hidden in the modules.
DI008445 Task ID
Technical ID of the task. For description, see Task ID.
DI008474 Report
Code (ID) of the status report
DI008475 Report / ID823
Code (ID) of the status report
DI008622 Requested start
Requested start date of the task at the time of creation/update of the status report. Upon creation/update of the status report, the value will be copied from the DI of the same name in the current planning (DT463 Task).
Note
- The corresponding data field is hidden by default but the user can unhide it if required.
DI008623 Requested end
The requested end date of the task at the time of creation/update of the status report. Upon creation/update of the status report, the value will be copied from the DI of the same name in the current planning (DT463 Task).
DI008624 Calc. start
Calculated start date of the task at the time of creation/update of the status report. Upon creation/update of the status report, the value will be copied from the DI of the same name in the current planning (DT463 Task).
DI008625 Calc. end
Calculated end date of the task at the time of creation/update of the status report. Upon creation/update of the status report, the value will be copied from the DI of the same name in the current planning (DT463 Task).
DI008626 Actual start
Actual start date of the task at the time of creation/update of the status report. Upon creation/update of the status report, the value will be copied from the DI of the same name in the current planning (DT463 Task).
Note
- The corresponding data field is hidden by default but the user can unhide it if required.
DI008627 Actual end
Actual end date of the task at the time of creation/update of the status report. Upon creation/update of the status report, the value will be copied from the DI of the same name in the current planning (DT463 Task).
DI008636 Task name
Name of the task
DI008765 Bar: milestone
Bar for the visualization of the milestones
DI008766 Deviation: req. end - calc. end end
Absolute deviation between the requested end date and the calculated end date of the task at the time of creation/update of the selected status report. Upon creation/update of the status report, the value will be copied from the DI of the same name in the current planning (DT463 Task).
DI008826 Bar: requested dates
Bar for the visualization of the interval between the Requested start date and Requested end date of the task at the time of creation/update of the selected status report
DI022286 Status
Date on which the status report was created
DI022287 Report name
Name of the status report
DI022288 Milestone trend analysis
DI022289 Released on
Date on which the status report was released
DI022312 VDI: project
Virtual data item for project
DI022313 VDI: report:
Virtual data item for status report
DI040168 Bar: master milestone
Bar for the visualization of the master milestones
DI057788 Deviation: req. end - calc. end end (text)
Absolute deviation between the requested end date and the calculated end date of the task at the time of creation/update of the selected status report with text specification (delay/float). The value is copied from the DI008766.
DI058220 Task
Functional identification number of the task. For description, see Task.
DI058221 WBS code
WBS code of the task in the status report (code for hierarchical display of tasks)
Note
- The corresponding data field is hidden by default but the user can unhide it if required.
DI058224 Parent task name
Name of the parent task
Note
- The corresponding data field is hidden by default but the user can unhide it if required.
DI008634 Effort used in %
The calculated work progress of the task in percent at the time of creation/update of the status report. When you create or update a status report, this value is copied from the DI of the same name in DT461 (Task).
Note
- The corresponding data field is hidden by default but the user can unhide it if required.
DI008639 Remaining costs
Remaining costs of the task at the time of creation/update of the status report. When you create or update a status report, this value is copied from the DI of the same name in DT461 (Task).
DI008640 Total costs
Total costs of the task at the time of creation/update of the status report. When you create or update a status report, this value is copied from the DI of the same name in DT461 (Task).
DI059633 Calc. start (baseline)
Calculated start date of the task from the baseline report
Note
- The corresponding data field is hidden by default but the user can unhide it if required.
DI059634 Calc. end (baseline)
Calculated end date of the task from the baseline report
Note
- The corresponding data field is hidden by default but the user can unhide it if required.
DI059630 Bar: planned dates (calculated dates from baseline)
Bar for the visualization of the interval between the calculated start date and the calculated end date of the task from the baseline report. The calculated dates fixed in the baseline report are called planned dates.
DI059639 Bar: actual start - work reporting date
Bar for the visualization of the interval between the dates of the first and last working hour report for the task at the time of creation/update of the selected status report
DI059349 Bar: calculated dates (traffic light)
Bar (with traffic light function) for the visualization of the interval between the calculated start date and the calculated end date of the task at the time of creation/update of the selected status report
DI008642 Milestone
Code (ID) for the Milestone parameter.
DI059262 Milestone: text
DI064924 Longest critical path BETA
Parameter which specifies whether the task lied on the longest critical path when the selected status report was created. The value is copied from the parameter of the same name (DT463 Task) at the time of creation of the status report.
Note
- The classical critical path (cf. CPM) ends on the project requested end date and is therefore always the path with the longest duration.
Caution
- With Server 39.5.25, PLANTA only provides the parameter for the calculation of the longest critical path. If you want to visualize the longest critical path in the schedules, you have to make respective customizing changes and embed the parameter in the task bar.
- This parameter can only be used if scheduling afterrun is activated in planta_scheduler.conf.