Dependencies MOD0099B8
Access
- Project (Proposal) panel → Further... → Dependencies
Information
- In this module, projects are displayed
- on which the completion of the current project depends (Dependent on area).
- and for the completion of which the selected project is required (Required for area), provided that the selected project has been selected in the corresponding projects in the Dependent on area.
- New dependencies can be created for the selected project.
Create dependency for the selected project
- Assign dependent projects button.
- A dialog module containing all projects will be displayed.
- Select the required project from the list by activating the respective checkbox and clicking on the Assign selected objects button.
- A dependency record in which the selected project is displayed is created automatically.
- The Requested end, Calc. end and Manager fields contain data from the corresponding project.
- If required, you can enter a comment in the Comment field.
- Save.
Details
- The dependencies created and displayed in this module are of purely informational nature. They have no effect whatsoever on the schedules of the projects concerned.
- There are two ways to illustrate dependencies between projects in PLANTA project:
- via cross-project (external) links (they have an effect on the task dates of the connected projects).
- by having external tasks displayed in your own schedule (they have no effect on the task dates of the connected projects).
Notes
- The dependencies can be created by users with multi-project manager, project manager, or multi-portfolio manager rights. If the user does not have the required rights, the button will not be displayed and the insert entry in the context menu will not be available.
- You cannot create a dependency to the project from which you try to create the dependency.