Overview: Plan and Calculate Effort
Information
If a project is divided into work packages, i.e. tasks, and the resources are assigned to individual tasks, resource or project managers can enter the planned effort in the corresponding field:
The planned effort for person, skill, and department resources is entered as time units ("hours" in the standard system) in the Remaining effort field.
The planned effort for cost and department resources is entered as time units ("Euro" in the standard system) in the Remaining effort field.
Details
Below you will find a brief tabular overview of the effort parameters for different project levels:
Project level (PR),
Task level (TA),
Resource assignment level / Level of assignment of resources to a task (TAR)
Load level / Level on which the effort of the resource is distributed to individual days (LOAD)
This overview also provides a description of the behavior in both initial planning and calculation of already running projects.
For a detailed description of the individual parameters, please use the links in the last column.
Description | Project is being planned (Actual start not yet set) | Project started (Actual start set) | Parameter | |
|---|---|---|---|---|
Remaining | Remaining vlaue, i.e., the remaining effort or the remaining costs of a project (proposal). This is the effort or the costs that are still required to complete the project. | Manual input in the resource assignment and subsequently
Exception: When you use the MAN load profile, the remaining values are entered at load level and are then summarized to resource assignment → task → project. |
Manual input or changes are only possible at resource assignment level. | Remaining effort (PR) |
Actual | Actual value, i.e. the actual workload or costs incurred in a project (proposal), i.e. the workload or costs that have already incurred for the completion of the project and posted to the project up to the time of assessment. | 0 |
| Actual effort (PR) |
Total | Sum value of Actual and Remaining values, i.e. the entire effort or costs of a project (proposal). | Automatic calculation on the respective level as soon as you have entered or changed Actual or Remaining and clicked outside the field. | Automatic calculation on the respective level as soon as you have entered or changed Actual or Remaining and clicked outside the field. | Total effort (PR) |