Information
-
The posting of costs and revenues can be locked or restricted via different parameters:
-
-
globally
-
with the Time recording key date planning model parameter in the Model and Model Parameters module. This parameter restricts the period for the recording/posting of actual data for all projects in the system.
-
-
per project
-
with the Locked parameter in the Attributes/parameters area in the Project Core Data module. As a result, it is not possible to record or post actual data (including both working hours and costs and revenues) to any of the project tasks.
-
-
per task
-
with the Task locked parameter in the Schedule module. This blocks the entry or posting of actual data (including both working hours and costs and revenues) for a specific task.
-
-
Customizing details
-
In the module customizer you can use the Time recording lock parameter to define how the above mentioned parameters behave.