Lock Time Recording

Information

  • The recording of hours worked can be locked or restricted via several parameters:

    • globally

    • per project

      • with the Locked parameter in the Attributes/parameters area in the Project Core Data module. As a result, it is not possible to record or post actual data (including both working hours and costs and revenues) to any of the project tasks.

    • per task

      • with the Task locked parameter in the Schedule module. This blocks the entry or posting of actual data (including both working hours and costs and revenues) for a specific task.


Customizing details

  • In the module customizer you can use the Time recording lock parameter to define how the above mentioned parameters behave.


See also: Overview: Working Time Recording , Lock Cost and Revenue Posting