For information
-
This topic describes the procedure of recording hours worked in PLANTA Hybrid when assigning a posting object to a PLANTA pulse card. For a general overview of the time recording options in PLANTA Hybrid and the synchronization of time recording data, see here.
-
This is a user-defined field of the posting object type from PLANTA project.
-
The field can be used on cards in order to assign a task from PLANTA project to them.
-
Hours recorded on this card are then posted to the corresponding task.
-
Select Posting Object
In order to be able to set a posting object on cards, you first have to create a user-defined field of the Posting object from PLANTA project type in PLANTA pulse. Further information
Procedure
-
Open the required card on which a posting object is to be set.
-
The field is displayed in a separate area on the card with the
symbol.
-
Click on Add.
-
In the search field, search for the desired process to which the working hours are to be posted.
-
It shows all tasks from PLANTA project on which the logged-on user can post.
-
If necessary, you can select a project in the Project field by which tasks are filtered.
-
Change Posting Object
Procedure
-
Open the required card on which the posting object is to be changed.
-
The field is displayed in a separate area on the card with the
symbol.
-
Click on Change.
-
In the search field, search for the desired process to which the working hours are to be posted.
-
It shows all tasks from PLANTA project on which the logged-on user can post.
-
In the Project field, you can select a project by which tasks are filtered.
-
Hours already recorded on the card will not be reposted if the posting object is changed afterwards.
Remove Posting Object
Procedure
-
Open the required card from which the posting object is to be remove.
-
The field is displayed in a separate area on the card with the
symbol.
-
Click on the X next to the field.
Hours already recorded on the card will not be deleted if the posting object is removed afterwards.
Recording of Hours Worked
Procedure
-
Open the required card on which the hours worked are to be recorded.
-
Open the Time Recording tab.
-
The selected booking object is displayed.
-
-
Enter the hours worked in the Worked field.
-
Add a comment if necessary.
-
Change the date if required.
-
Click on Save or confirm by pressing CTRL/Shift + Enter.
-
The recorded hours are now displayed in a table below the input area.
-
The recorded hours are posted to the task from PLANTA project that has been selected as posting object.
Change/Delete Hours Worked
Procedure
-
Open the required card on which you want to change hours worked.
-
Open the Time Recording tab.
-
In the table, click on the hourly value that you want to change.
-
Make the changes in the upper Edit time recording area.
-
Click on Save or confirm by pressing CTRL/Shift + Enter.
-
Via the Cancel button, the editing mode can be quit without saving changes.
-
The changes are sent to PLANTA project as well.
Display in the Time Recording panel
-
In the Time Recording panel of PLANTA pulse, the recorded hours are displayed on the corresponding card.
-
Information about the task on which the hours were posted is also displayed.
-
Additional working hours can also be recorded directly in the Time Recording panel. Further information