Information
-
The portfolio budget determines which costs may generally occur in the planning objects of a portfolio.
Where can I budget a portfolio?
In the Budget module of the required portfolio.
Open the portfolio
-
by clicking on the Portfolios menu item button in the Planning area of the user menu and
-
clicking on the link on the ID of the portfolio in the List (Portfolio) module that opens.
Subsequently switch to the Budget module tab in the opened portfolio panel.
Note
-
In PLANTA, the portfolio budget is not defined and approved per entire portfolio but per year.
Specify Budget
Procedure
-
Click on the Insert yearly tranche button in the action bar.
-
Select the year(s) for which you want to budget the portfolio in the Create Yearly Tranche dialog module.
-
Click on the Assign selected objects button. The respective yearly tranche is created.
-
In the yearly tranche, the summarized cost and budget data of all planning objects of the portfolio will automatically be displayed per cost type group.
-
-
Enter the portfolio budget for each cost type group manually in the Portfolio budget column.
-
Save.
You can tell whether the budget of the planning objects exceeds the portfolio budget by the color of the Deviation and % deviation fields. Further information
Approve Budget
Procedure
-
Click on the Approval button for the required year.
-
Confirm the Do you really want to approve the period? query with Yes.
-
The Approved checkbox is activated and thus the budget for the period is approved.
-
An approved period cannot be edited or deleted. To do so, you first have to cancel the approval.
-
Cancel Approval per Budget Period
Procedure
-
Click on the Approval button for the required year.
-
Confirm the Do you really want to cancel the budget approval for this period? query with Yes.
-
The Approved checkbox will be deactivated.
-
This means the budget is no longer approved and can be edited or deleted.
-